Edward Court Pipeline Replacement

This project involves the installation of approximately 300 lineal feet of new 8-in and 4-in C900 PVC pipeline, and the replacement of three (3) services on Edward Ct, south of Lou Place.  This project is scheduled to begin between March and June 2019 and should be completed by July or August 2019.  Affected customers will be contacted by District personnel a few weeks in advance of the project construction start-up, and will be provided with specific information related to the construction schedule and aspects of the project that may be anticipated to affect our customers.